ARCO/Murray Completes Laundry for Crown Health Care

Posted July 23, 2019 at 7:11 pm



ARCO/Murray, Downers Grove, IL, recently completed an 86,500-square-foot healthcare laundry build-out for Crown Health Care in Lakeland, FL. The project was a complete design-build solution including architectural and engineering design, permitting, building modifications, process piping and electrical work, according to a news release.

In order to open the new plant ahead of schedule, both the design time and construction schedule were compressed, cutting the overall project duration by a month. The entire laundry equipment package was provided by Pellerin Laundry Machinery Supply Co. and included Milnor washroom equipment, Chicago finishing equipment, Kemco water systems and Softrol rail.

This was ARCO/Murray’s first project with Crown Health Care. Max Potvin served as project manager and Glenn Broome was the project superintendent.

124